Dhaka–Shariatpur Four-Lane Highway Project Remains Incomplete Despite Two Deadline Extensions
- Update Time : 09:34:10 am, Sunday, 15 November 2026
- / 33 Time View

Construction of the Dhaka–Shariatpur four-lane highway remains unfinished despite two extensions to the project deadline. The Roads and Highways Department (RHD) has applied for a third extension, citing complications over land acquisition.
Local residents, however, allege that construction work has come to a complete halt across all three project packages. They say there are no workers or machinery at the project sites, and no one can say when the work will be completed.
Local residents Mosharraf Hossain and Abul Kalam said construction of the bridge over the Kirtinasha River at Kazir Hat had not even reached the halfway mark in six years. They added that no work had been carried out there for the past three months.
Sharif Hossain, a representative of contractor Mir Habibur Alam and Rana Builders, said the company had been unable to complete the work within the stipulated timeframe because it had not received possession of the required land.
According to the Shariatpur Roads and Highways Department, the Ministry of Road Transport and Bridges took the initiative in 2020 to construct a road connecting Shariatpur district town with the Padma Bridge Expressway to improve travel between the district and Dhaka.
Subsequently, a Tk 1,682 crore project was approved to upgrade the existing 18-foot-wide road from the district town to Nawdoba into a four-lane highway.
The district administration’s land acquisition office began acquiring 105 hectares of land for the 27-kilometre road expansion project. Construction started in 2021.
Project documents show that the work was divided into three packages and awarded to three contractors.
Mir Habibur Alam and Rana Builders was assigned a 13.5-kilometre stretch from Shariatpur district town to the Jajira Upazila headquarters. Messrs Saleh Ahmed received responsibility for a 12-kilometre section from Jajira T&T to Nawdoba. Jamil and Zahid Iqbal Enterprise Private Limited was awarded the construction of two bridges and 1.5 kilometres of connecting roads.
Of the three packages, land acquisition remains incomplete for a two-kilometre section of the stretch from the district town to Jajira. The district administration’s Land Acquisition (LA) section has yet to complete the process for this portion.
Shah Alam, an engineer at Mir Habibur Alam and Rana Builders, said construction on the two-kilometre section could not begin because the land had not been handed over.
“That is the responsibility of the DC office. We cannot take possession ourselves. Once the Roads and Highways Department hands over the land to us, we will be able to start work,” he said.
Meanwhile, the project’s second extended deadline expired on June 30.
Attempts to contact the other two contractors, Messrs Saleh Ahmed and Jamil and Zahid Iqbal Enterprise Private Limited, found that their representatives were either abroad or in hiding, according to the report.
Drivers and Passengers Face Severe Hardship
After years of delays, the unfinished highway is now riddled with potholes and damaged sections. Vehicles continue to use the road despite the growing safety risks, delays and accidents, causing severe hardship for drivers and passengers.
During the rainy season, the highway becomes covered with mud and water, multiplying the difficulties for commuters.
Abdul Hannan, who drives a bus daily on the Shariatpur–Dhaka route, said travelling along the road had become extremely difficult. Buses frequently break down after mechanical parts are damaged while navigating the potholes, bringing traffic on the highway to a standstill.
Another driver, Abdur Karim Hossain, said motorists regularly had to spend at least an hour stuck in traffic congestion on the highway.
“This has become a daily occurrence,” he said.
Regular passengers Rahim Mollah and Masud Bepari said accidents were frequent on the road, with vehicles occasionally overturning.
Authorities Promise to Resume Work Soon
Ahad Rahman Khan, sub-divisional engineer of the Shariatpur Roads and Highways Department, attributed the prolonged delay to complications involving land acquisition.
He said some land acquisition issues remained unresolved under LA Cases Nos. 14, 15 and 16. Work on the approach road to Premtala Bridge had also been suspended because of land acquisition complications.
However, he said those land acquisition issues had now been resolved and construction would resume soon.
Regarding the bridge at Kazir Hat, the engineer said work had been suspended due to adverse weather conditions. Construction is expected to resume at the end of November.
He added that a proposal had been sent to extend the project’s deadline by another year. If necessary, new contractors would be appointed to ensure the work is completed quickly.
“Some of the contractors working on the road are facing complications. We have already sent them notices. If they do not resume work soon, we will cancel their contracts and move forward by appointing new contractors,” he said.